Gantry cranes 30+10 t, transit construction site, Toronto
Home / Products / Tunnelling
TUNNELLING EQUIPMENT

Tunnelling equipment: segment handling and shaft gantry cranes

A specialisation, not an occasional activity: two current Eden Tech projects, backed by sixteen earlier tunnelling supplies our team worked on — segment handling behind the TBM, shaft and muck-removal gantries, machines that fit the tunnel the tunnel already is. Tunnelling (tunneling) equipment designed and built in Italy.

CAPABILITIES

What a tunnel contractor screens suppliers on

Segment handling behind the TBM

Forwarding systems, backup wagons, MSV tyre trolleys and segment positioning — on slopes up to 15%.

Shaft handling and muck removal

Gantry cranes with full capacity on the overhang and negative hook travel, serving the shaft directly from surface level.

Work in a confined section

Machines that adapt to the tunnel profile, electro-hydrostatic drives for limited ventilation, no manoeuvre that a tunnel has no room for.

Non-European standards

CSA and OSHA compliance — demonstrated on a delivered project in Toronto, not declared in a brochure.

The critical path

Underground, every manoeuvre costs time on the whole project. A handling cycle with one manoeuvre fewer is worth far more than on a surface site.

2 + 16 supplies

Two Eden Tech projects, in the UK and Canada; sixteen earlier ones our team worked on at Paolo De Nicola S.p.A. and Eden Technology Srl, in Hong Kong, Qatar, Greece, Norway, Italy and China.

MOBILIFT 16 t in a road tunnel, London
London, UK · 2023 · Ref. E481

MOBILIFT 16 t — road tunnel, London

A machine that shapes itself to the tunnel: it takes a concrete segment from a trolley, travels with it on the overhang, rotates it and sets it in position.

  • Self-adapting front wheel supports. The machine follows the tunnel profile; no reconfiguration between curved and flat sections.
  • Full capacity on the overhang. The segment is carried where it has to be placed, not where it is convenient to hold it.
  • Hook and lifting structure travelling right to left. Both sides of the tunnel are served without turning the machine around.
  • The whole cycle performed by one machine. Pick, travel, rotate and place: no transfer to a second machine, no second lift.
  • Electro-hydrostatic drive. Suited to a confined environment with limited ventilation.
Project, machine & technical data

The project

A road tunnel project in London required concrete elements, taken from the MSVs (multi-service vehicles), to be positioned inside the tunnel. A tunnel is the most constrained working environment a lifting machine can be given: the cross section is fixed, the profile changes between straight and curved sections, and the floor is not a flat slab. The machine has to fit the tunnel the tunnel already is.

The machine

The MOBILIFT 16 t runs on tyres and is electro-hydrostatic. Its front wheel supports are self-adapting and the rear steering allows an easy change of inclination. The hook is on the overhang and can move from right to left, as can the entire lifting structure — which is what allows a segment to be placed on either side of the tunnel without the machine having to turn around.

Technical data

Machine type
Electro-hydrostatic lifting machine on tyres, for tunnel work
Capacity (SWL)
16 t on the overhang
Front wheel supports
Self-adapting to the curved and flat sections
Rear steering
Easy change of inclination
Handling cycle
Segment picked from the trolley, carried on the overhang, rotated and placed
Client
Tunnel contractor — United Kingdom
MOBILIFT 16 t — road tunnel, LondonMOBILIFT 16 t — road tunnel, LondonMOBILIFT 16 t — road tunnel, LondonMOBILIFT 16 t — road tunnel, LondonMOBILIFT 16 t — road tunnel, London
Gantry crane 30+10 t at works testing
Toronto, Canada · 2025 · Ref. E702

Two gantry cranes 30+10 t — transit shaft, Toronto

Electric gantry cranes for shaft work: full capacity on the overhang, negative hook travel, CSA and OSHA compliant.

  • Full capacity on the overhang. The rated load is available beyond the legs, where the shaft is.
  • High speed hoisting.
  • Negative hook travel. The load is lowered below crane level: the shaft is served directly from surface level.
  • Light upper trolley. Less dead load along the girder, therefore less steel for the same capacity, and lower transport and erection costs.
  • CSA and OSHA compliance. Design, documentation and components to the North American framework.
Project, machine & technical data

The project

Handling into a shaft is a vertical problem with a horizontal constraint. The load is picked up at surface level, moved horizontally to the shaft opening, and then lowered well below the level of the crane rails. On an urban transit project the shaft is the only way in and out of the works, so the crane is the bottleneck of the whole site: its availability governs the progress of everything underground.

The machine

Heavy-duty electric gantry cranes with full capacity on the overhang and negative hook travel. The upper trolley is light, since it only carries the pulley blocks: moving the winches off the trolley reduces the dead load along the girder, and with it the girder section, the wheel loads and the size of the whole structure — on a site where every delivery has to be routed through city streets.

Technical data

Units supplied
No. 2
Capacity (SWL)
30 t main hoist + 10 t auxiliary
Overhang
Full capacity available on the overhang
Hook travel
Negative travel, below crane level
Trolley
Light upper trolley, carrying the pulley blocks only
Standards
Fully compliant with CSA and OSHA
Client
Transit infrastructure contractor — Canada
Two gantry cranes 30+10 t — transit shaft, TorontoTwo gantry cranes 30+10 t — transit shaft, TorontoTwo gantry cranes 30+10 t — transit shaft, TorontoTwo gantry cranes 30+10 t — transit shaft, TorontoTwo gantry cranes 30+10 t — transit shaft, Toronto
EXPERIENCE OF OUR TEAM

Sixteen earlier tunnelling supplies

Before Eden Tech, members of our team designed and built tunnelling equipment at Paolo De Nicola S.p.A. and at Eden Technology Srl, for projects in Hong Kong, Qatar, Greece, Norway, Italy and China.

Ref.MachineApplicationCountry
I27Five high-performance bridge gantries 50 t for muck removalMuck removalQatar
L11EBR150 gantry crane 150 tShaft handlingHong Kong
I20High-performance gantry crane 52 t for muck removal, spreader and sparesMuck removalHong Kong
N25Eleven MSV tyre trolleys, in three suppliesTBM logistics (MSV)Norway
L27Tunnelling tyred trolley 30 t on 15% slope; pipe positioning systemInclined tunnelGreece
I14TBM backup wagons, segment forwarders, forwarding system on a 12% slope; gantry crane 55 tTBM supportItaly / China

Work orders of Paolo De Nicola S.p.A. and Eden Technology Srl on which members of today’s Eden Tech team worked. They are listed as the professional experience of our people, not as Eden Tech supplies.

Ask for the full reference list

Tell us the constraint you cannot change.

We will tell you whether a machine can be built around it — and roughly what it takes.

Talk to our engineers